Our Process.

From reaching out to final walk-through, our process is clear and simple. Estimated total timeframe from initial inquiry to completion is 9–12 months.

1

Introductory call, complimentary property visit

Time Frame:

Within 2 weeks of your initial inquiry

Investment:

$0

During the Introductory Call we will answer any questions you have and schedule a time for one of the principles of AZ-ADU to come by your home for a Complimentary Property Visit. At the Complimentary Property Visit we will walk your property with you, review the desired location of your ADU, note any unique features, preliminarily identify utility connections, discuss a preliminary budget, financing options, a preliminary timeline and answer any questions you have.

Az Adu leading ADU developers in the Phoenix Metropolitan Area

2

Team Visit

Time Frame:

Scheduling 2 +/- weeks

Investment:

$750

If you like what you hear on the Introductory Call & Complimentary Property Visit and want to move to the next step with AZ-ADU we will assemble our team of professionals including a licensed plumber, licensed electrician and utility locating company to visit your property. In addition our draftsman and civil engineer (if required) will review your property. The team will assess your property condition, governmental regulations, map existing & future utilities, and confirm your ADU design vision. By taking this step we can ensure we have identified the cost components unique to your property and move towards providing you with a Comprehensive Proposal providing you with a budget you can rely on moving forward.

Az Adu leading ADU developers in the Phoenix Metropolitan Area

3

Comprehensive Proposal

Time Frame:

1-2 weeks

Investment:

$0

We will assemble the reports from the Team Visit, discuss with all Team Members your property & unique features and prepare a Comprehensive Proposal for you for the design, permit and build of your ADU…. start to finish! The Comprehensive Proposal will include the reports from the Team Visit, a site plan of your property and a construction agreement with AZ-ADU Builders, LLC.

Az Adu leading ADU developers in the Phoenix Metropolitan Area

4

Signed Proposal

Time Frame:

4-8 weeks

Investment:

15% of budget

When you decide to move forward and engage AZ-ADU Builders, LLC to build your ADU we will work with you to finalize the design of your ADU. In addition, a licensed Civil Engineer will prepare a soils report for your property. At the same time our draftsman will prepare the necessary final set of drawings including the AZ-ADU floor plan you chose, your property site plan and utility connections. Once all documents are ready to submit AZ-ADU will coordinate getting the plans logged into the City plan review portal to begin the review process.

Az Adu leading ADU developers in the Phoenix Metropolitan Area

5

Permit Tracking

Time Frame:

3-4 months

Investment:

$0

We will monitor the entire process and keep you informed as the City reviews your plans. We will inform you once a permit is obtained.

Az Adu leading ADU developers in the Phoenix Metropolitan Area

6

Build

Time Frame:

5-7 months

Investment:

35% - upon obtaining permit, 20% - progress payment, 20% - progress payment

AZ-ADU Builders, LLC and its subcontractors will handle the construction of your ADU up to the final punch list.

Az Adu leading ADU developers in the Phoenix Metropolitan Area

7

Move in!

Time Frame:

Immediate!

Investment:

10% - upon Certificate of Occupancy

The most exciting step in the process….we hand you the keys to your complete and ready to enjoy your ADU!

Az Adu leading ADU developers in the Phoenix Metropolitan Area